Belgrade, June 19, 2025

On the session held on June 19, 2025, upon the request of the Joint Stock Company "Elektromreža Srbije", the transmission system operator, the Council of the Energy Agency of the Republic of Serbia has adopted decisions approving operational limitations for battery energy storage systems and generation facilities connecting to the transmission system.

According to the Energy Law, the transmission system operator may offer a connection subject to operational limitations, provided such limitation is approved by the Agency.

In accordance with the Energy Law and the regulations adopted based on it, the Joint Stock Company "Elektromreža Srbije" adopted the Rules for Connecting Facilities to the Transmission System which define the technical conditions for connection. The connection conditions for a facility are determined in the connection study prepared by the transmission system operator. If the results of the study indicate the need for operational limitations, these are defined as the method of connection to eliminate overloads in the transmission system caused by the facility for which the connection request was submitted.

For each facility where operational limitations were deemed necessary, the transmission system operator submitted requests for approval to the Agency, based on which the Council of the Agency made decisions.